Solar and Battery for New Construction/ADU Projects
Please click to video below to see how to make a new build Solar and Battery ready:

Title 24 Requirements
Your architect will have a Title 24 consultant that will work on getting your project a score that will Pass. This will generate the DC system size that is required for your New Home or ADU Project. Many often have a battery nowadays as well.
Best Practices
When installing solar and battery on a new home or ADU, there are a number of considerations and strategies that will set your home or ADU up for success:
-Install the solar footings and attic boxes during roofing, on top of the underlayment.
-Run your flex inside of the walls while they are still open. Think after MEP inspection but before insulation, and then pull the wire ahead of time, not after drywall.